EXN Status Page
All Systems Operational
Client Portal ? Operational
Shared Hosting ? Operational
DC Connect ? Operational
IP Transit Services ? Operational
Leased Lines Operational
Virtual Data Centre (vDC) - Global Switch 2 ? Operational
Virtual Data Centre (vDC) - Virtus Enfield ? Operational
Datacentres Operational
Global Switch 2 Operational
Reading Operational
Telecity Meridian Gate Operational
Virtus Enfield Operational
Virtus Hayes Operational
Volta GSS Operational
Telehouse North Operational
Telehouse East Operational
Virtus Slough Operational
Equinix LD8 Operational
Operational
Degraded Performance
Partial Outage
Major Outage
Maintenance
Scheduled Maintenance
As advised by Cisco TAC, EX Networks will be performing a software upgrade on the core router located in Telehouse North – zephyr.thn.exn.uk. We will be upgrading the version of IOS-XR which will introduce several bug fixes to ensure service stability as well as a number of new features.

Due to the nature of this upgrade, the router and line cards will need to be reloaded. This will cause an outage for directly connected clients, and BGP sessions both with clients and upstream Tier-1 partners as well as peering exchanges.

At EXN we designed our network with maintenance and outages in mind, and as such upstream connections and linknets between data centres will be gracefully failed over before the reload. This means only directly connected clients and client BGP sessions will be “DOWN” during the reload. Other services should be considered “AT RISK” during this work.

As these routers have several line cards and FPGA’s there will be several reloads of individual components. Therefore, all client facing ports will be shutdown and EXN engineers will confirm the stability of the device before bringing the ports back up.

Over the next few days the affected clients will be contacted individually by EXN.

Location: Telehouse North
Start: 23/03/2019 – 00:00 (UTC +0)
End: 23/03/2019 – 06:00 (UTC +0)
Affected Services: Connectivity Services
Reason: Software Update
Classification: Service Affecting (Directly Connected Clients) / At Risk
Rollback plan: Revert to previous version of IOS-XR

Please don’t hesitate to contact us through the usual channels should you have any questions regarding this maintenance.
Posted on Feb 18, 11:23 GMT
Past Incidents
Mar 21, 2019

No incidents reported today.

Mar 20, 2019

No incidents reported.

Mar 19, 2019

No incidents reported.

Mar 18, 2019

No incidents reported.

Mar 17, 2019

No incidents reported.

Mar 16, 2019
Completed - The scheduled maintenance has been completed.
Mar 16, 02:38 GMT
In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
Mar 16, 00:00 GMT
Scheduled - As advised by Cisco TAC, EX Networks will be performing a software upgrade on the core router located in Telehouse East – runner.the.exn.uk. We will be upgrading the version of IOS-XR which will introduce several bug fixes to ensure service stability as well as a number of new features.

Due to the nature of this upgrade, the router and line cards will need to be reloaded. This will cause an outage for directly connected clients, and BGP sessions both with clients and upstream Tier-1 partners as well as peering exchanges.

At EXN we designed our network with maintenance and outages in mind, and as such upstream connections and linknets between data centres will be gracefully failed over before the reload. This means only directly connected clients and client BGP sessions will be “DOWN” during the reload. Other services should be considered “AT RISK” during this work.

As these routers have several line cards and FPGA’s there will be several reloads of individual components. Therefore, all client facing ports will be shutdown and EXN engineers will confirm the stability of the device before bringing the ports back up.

Over the next few days the affected clients will be contacted individually by EXN.

Location: Telehouse East
Start: 16/03/2019 – 00:00 (UTC +0)
End: 16/03/2019 – 06:00 (UTC +0)
Affected Services: Connectivity Services
Reason: Software Update
Classification: Service Affecting (Directly Connected Clients) / At Risk
Rollback plan: Revert to previous version of IOS-XR

Please don’t hesitate to contact us through the usual channels should you have any questions regarding this maintenance.
Feb 18, 11:23 GMT
Mar 15, 2019
Resolved - This incident has been resolved.
Mar 15, 20:25 GMT
Update - After a period of stability, EXN will be putting this link back into service at 20:00 GMT today.
Mar 15, 17:12 GMT
Monitoring - Our fibre provider fixed the fault in the early hours of this morning. EXN are continuing to monitor the link and will be bringing the fibre back into service this evening. We are also waiting to hear back on the cause of the issue.
Mar 15, 08:00 GMT
Update - Our fibre provider is currently investigating the issue. All systems remain stable however the site should be considered "AT RISK" during this time.
Mar 14, 18:30 GMT
Investigating - EXN have been alerted to a drop in light levels between Telehouse North and Virtus Enfield, the link is still up, but as a precaution we are moving traffic away from this link and we will be raising this with our fibre provider.
Mar 14, 17:05 GMT
Mar 13, 2019

No incidents reported.

Mar 12, 2019

No incidents reported.

Mar 11, 2019

No incidents reported.

Mar 10, 2019

No incidents reported.

Mar 9, 2019
Completed - The scheduled maintenance has been completed.
Mar 9, 06:00 GMT
In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
Mar 9, 00:00 GMT
Scheduled - As advised by Cisco TAC, EX Networks will be performing a software upgrade on the core router located in Equinix LD8 – toucan.ld8.exn.uk. We will be upgrading the version of IOS-XR which will introduce several bug fixes to ensure service stability as well as a number of new features.

Due to the nature of this upgrade, the router and line cards will need to be reloaded. This will cause an outage for directly connected clients, and BGP sessions both with clients and upstream Tier-1 partners as well as peering exchanges.

At EXN we designed our network with maintenance and outages in mind, and as such upstream connections and linknets between data centres will be gracefully failed over before the reload. This means only directly connected clients and client BGP sessions will be “DOWN” during the reload. Other services should be considered “AT RISK” during this work.

As these routers have several line cards and FPGA’s there will be several reloads of individual components. Therefore, all client facing ports will be shutdown and EXN engineers will confirm the stability of the device before bringing the ports back up.

Over the next few days the affected clients will be contacted individually by EXN.

Location: Equinix LD8
Start: 09/03/2019 – 00:00 (UTC +0)
End: 09/03/2019 – 06:00 (UTC +0)
Affected Services: Connectivity Services
Reason: Software Update
Classification: Service Affecting (Directly Connected Clients) / At Risk
Rollback plan: Revert to previous version of IOS-XR

Please don’t hesitate to contact us through the usual channels should you have any questions regarding this maintenance.
Feb 18, 11:22 GMT