Virtus Slough - "B" Feed Switch
Scheduled Maintenance Report for EX Networks
Completed
We have been informed by the data centre that this maintenance has been postponed. Another maintenance window will be announced in due course.
Posted Nov 18, 2017 - 19:08 GMT
Update
Please be advised that the transfer back planned for this Saturday has been postponed for 2 weeks until Saturday 18th November at 23:00.
Posted Nov 03, 2017 - 09:52 GMT
Scheduled
On Saturday 4th November Virtus are completing essential UPS maintenance. During this time the "B" feed of this suite will be switched back to raw mains causing a very short outage on the "B" feed.

If you have any queries, please do not hesitate to contact us quoting the ticket reference number T20170915.0050.
Posted Oct 30, 2017 - 10:40 GMT