VMware vDC Software Updates (Global Switch 2 & Virtus Enfield)
Scheduled Maintenance Report for EX Networks
Completed
The scheduled maintenance has been completed.
Posted Apr 01, 2018 - 00:16 BST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Mar 31, 2018 - 18:00 BST
Scheduled
EXN will be performing essential maintenance on the management functions and hypervisors of our VMware services. During this time we will be upgrading vCenter, ESX, vCloud Director and NSX to their latest versions in order to facilitate new features as well as security and bug fixes.

vCloud Director will be upgraded to version 9.1 which brings a number of improvements to the new HTML5 portal.

The upgrade procedure and new versions have been tested thoroughly in our lab and we expect the disruption to be kept to a minimum.

Please note this maintenance with only affect the management functions of your VMs. The VMs themselves will not be affected by this maintenance.

Location: Global Switch 2, Virtus Enfield
Start: 31/03/2018 - 18:00 BST (UTC +1)
End: 01/04/2018 - 01:00 BST (UTC +1)
Affected Services: VMware vDC Management Functions
Reason: Upgrades
Classification: At Risk
Rollback plan: Remove Patches
Posted Mar 27, 2018 - 14:23 BST