At Risk - Virtus Enfield - Additional Generator Maintenance
Scheduled Maintenance Report for EX Networks
Completed
The scheduled maintenance has been completed.
Posted Jul 12, 2017 - 18:00 BST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jul 10, 2017 - 08:00 BST
Scheduled
VIRTUS LONDON1 (Enfield) have informed us that following the recent Generator maintenance at LONDON1, the service engineer has recommended carrying out additional minor remedial works on the non-return valves on the generators. This will be conducted between Monday 10th July 2017 08:00 BST and Wednesday 12th July 2017 18:00 BST.

All critical supplies, which include all customer data halls and mechanical power feeds are UPS backed, with a minimum UPS battery autonomy time of approx. 55 minutes.

At present, the Generators have a resilience of N+1 and the works will be carried out on one Generator at a time ensuring that the site is always supported.

If you have any queries, please do not hesitate to contact us.
Posted Jul 05, 2017 - 16:48 BST