At Risk - Virtus Slough - 6 monthly UPS Maintenance - Mechanical Services
Scheduled Maintenance Report for EX Networks
Completed
The scheduled maintenance has been completed.
Posted Aug 19, 2017 - 19:00 BST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Aug 19, 2017 - 08:00 BST
Scheduled
VIRTUS LONDON4 (Slough) have informed us that the scheduled 6 monthly UPS Maintenance will be conducted on Saturday 19th August between the hours of 08:00 BST and 19:00 BST. This will affect the UPS supporting the Mechanical Services of the facility only (the IT Load UPS Maintenance is scheduled for June).

The UPS Modules are deployed in an N+1 configuration and the works will be carried out on one unit at a time ensuring that the site is always supported. During this maintenance you will see no interruption to service.

If you have any queries, please do not hesitate to contact us.
Posted May 31, 2017 - 10:22 BST