In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
Apr 28, 2026 - 11:00 BST
Scheduled - Repair works are underway on a subsea cable that connects the UK and the Republic of Ireland.
This work affects one of the EXN network routes between London and Dublin.
No impact to services is expected, but due to reduced resilience we regard Network Services at our Dublin data centre to be **At Risk** during the maintenance activity.
The works are expected to be completed between 28th April and 3rd May.
Location: DRT Dublin (DUB10) Start Date: 2026-04-28 End Date: 2026-05-03 Affected Services: Connectivity Services Classification: At Risk Reason: Supplier Maintenance
Should you have any questions regarding this maintenance, please do contact us through the usual channels.
Apr 28, 202611:00 - May 4, 202600:00 BST
Client Portal
Operational
Shared Hosting
Operational
DC Connect
Operational
Wave Connect
Operational
IP Transit Services
Operational
Leased Lines
Operational
Virtual Data Centre (vDC) - Global Switch East
Operational
Virtual Data Centre (vDC) - Virtus Enfield
Operational
Datacentres
Under Maintenance
DRT Dublin (DUB10)
Under Maintenance
DRT Oliver's Yard (LHR18)
Operational
Equinx LD7
Operational
Equinix LD8
Operational
Global Switch London East (formerly Global Switch 2)
Operational
Iron Mountain AMS1
Operational
Telehouse East
Operational
Telehouse North
Operational
Telstra London Hosting Centre (LHC)
Operational
Verne London (formerly Volta Data Centres)
Operational