At Risk - Virtus Enfield - Generator Installation
Scheduled Maintenance Report for EX Networks
Completed
The scheduled maintenance has been completed.
Posted Mar 15, 2018 - 20:00 GMT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Mar 05, 2018 - 08:01 GMT
Scheduled
VIRTUS LONDON1 (Enfield) have informed us that during the period of 5th – 15th March, they will be integrating an additional standby generator into the back-up power system at LONDON1 (Enfield).

These works have been planned in such a way as to minimise any impact on the resilience of the site however, during the process they will need to carry out mains failure scenarios on the site to prove the installation. The building UPS systems will support all services during the mains failure tests. All critical supplies which include all customer data halls and mechanical power feeds are UPS backed, with a minimum UPS battery autonomy time of approx. 45 minutes.

If you have any queries, please do not hesitate to contact us quoting the ticket reference number T20180213.0059.
Posted Feb 17, 2018 - 08:12 GMT