Equinix LD8 to GS2 Fibre Maintenance (AT RISK)
Scheduled Maintenance Report for EX Networks
Completed
The scheduled maintenance has been completed.
Posted Oct 22, 2019 - 23:25 BST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Oct 22, 2019 - 22:00 BST
Scheduled
Our fibre provider is performing some at risk maintenance between Equinix LD8 and Global Switch 2 (GS2) on 22/10/2019. This work will only affect a single link between these sites, and is classified as "AT RISK" therefore no client impact is expected.

Location: Equinix LD8, Volta, Global Switch 2
Start: 22/09/2019 - 22:00 BST (UTC +1)
End: 23/09/2019 - 01:00 BST (UTC +1)
Affected Services: Network Services
Reason: Supplier Maintenance
Classification: At Risk

Please don’t hesitate to contact us through the usual channels should you have any questions regarding this maintenance.
Posted Oct 16, 2019 - 17:22 BST
This scheduled maintenance affected: Datacentres (Equinix LD8, Global Switch 2).