VMware vDC Management Portal Upgrade (Global Switch 2 & Virtus Enfield)
Scheduled Maintenance Report for EX Networks
Completed
The scheduled maintenance has been completed.
Posted Apr 08, 2019 - 21:01 BST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Apr 08, 2019 - 19:00 BST
Scheduled
On Monday 8th April 2019, EXN will be upgrading our vDC (Virtual Data Centre) management portal for both the Global Switch 2 and Virtus Enfield vDCs. This will affect the management interfaces for customers using https://vdc.exn.uk/

During the maintenance, EXN will be upgrading our vCloud Director installation to version 9.5 which has a number of new features including enhancements to the new HTML5 portal. The upgrade procedure has been tested several times in our lab environment and we expect the work to go smoothly. While the maintenance will bring down all management functions for your VMs, the machines themselves will remain unaffected.

Location: Global Switch 2, Virtus Enfield
Start: 08/04/2019 - 19:00 BST (UTC +1)
End: 08/04/2019 - 21:00 BST (UTC +1)
Affected Services: VMware vDC (https://vdc.exn.uk)
Reason: Service Upgrade
Classification: Loss of Management Functions
Rollback plan: Revert to previous version
Posted Apr 02, 2019 - 17:02 BST
This scheduled maintenance affected: Virtual Data Centre (vDC) - Global Switch 2 and Virtual Data Centre (vDC) - Virtus Enfield.