Equinix LD8 - Power Feed Maintenance

Scheduled Maintenance Report for EX Networks

Completed

The scheduled maintenance has been completed.
Posted Aug 11, 2020 - 22:00 BST

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Aug 11, 2020 - 21:00 BST

Scheduled

Equinix have annouced a scheduled power maintenance that will affect our network services in Equinix LD8. Equinix will be transferring our rack power supplies to a new electrical infrastructure. Only one power supply will be transferred at a time. Checks will be made to ensure that all services are live before changing the alternative power supply. The works will be undertaken by skilled Equinix engineers. This activity is fully scripted and may include the use of equipment system vendors and service providers. During this maintenance network services will be classed as "AT RISK".

Location: Equinix LD8
Start: 2020-08-11 - 21:00 BST (UTC + 1)
End: 2020-08-11 - 22:00 BST (UTC + 1)
Affected Services: Connectivity Services
Reason: Supplier Maintenance
Classification: At Risk
Rollback plan: Not Applicable
Posted Jul 29, 2020 - 13:09 BST
This scheduled maintenance affected: Datacentres (Equinix LD8).