Planned Maintenance - Virtus LON1 Enfield - Switch Reload

Scheduled Maintenance Report for EX Networks

Completed

The scheduled maintenance has been completed.
Posted Aug 09, 2022 - 00:27 BST

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Aug 08, 2022 - 22:00 BST

Scheduled

During this maintenance window EXN will be performing a graceful reload of our device "yakima.enf" in Virtus LON1 Enfield.

EXN will migrate traffic traversing the device being worked on prior to any upgrades, meaning only directly connected clients will be affected. These clients are going to be contacted directly.

Location: Virtus LON1 Enfield
Affected Services: Network Services, vDC Platform
Reason: Proactive Firmware Upgrade
Classification: At risk and service affecting for directly connected clients

Should you have any questions regarding this maintenance please don’t hesitate to contact us through the usual channels.
Posted Jul 27, 2022 - 11:32 BST
This scheduled maintenance affected: Virtual Data Centre (vDC) - Virtus Enfield and Datacentres (Virtus LON1 Enfield).