Global Switch 2 - Power Maintenance

Scheduled Maintenance Report for EX Networks

Completed

The scheduled maintenance has been completed.
Posted Jan 18, 2020 - 05:30 GMT

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jan 18, 2020 - 04:30 GMT

Scheduled

We have been notified by Global Switch of some upcoming planned maintenance at the Global Switch 2 data centre. They will be performing an annual "Circuit Break Confidence Switching" test in conjunction with UK Power Networks. There is no impact to power expected however the building should be considered "AT RISK" during this maintenance window

Location: Global Switch London 2 (East)
Start: 2020-01-18 - 04:30 GMT (UTC)
End: 2020-01-18 - 05:00 GMT (UTC)
Affected Services: Power
Reason: Preventative Maintenance
Classification: At Risk
Posted Jan 08, 2020 - 14:36 GMT
This scheduled maintenance affected: Datacentres (Global Switch East (formally Global Switch 2)).