Scheduled Network Maintenance – Virtus LON1 Enfield - CANCELLED

Scheduled Maintenance Report for EX Networks

Completed

The network maintenance originally scheduled for Thursday 16th October 2025 21:00 BST has been cancelled.
The activity will be rescheduled and fresh notifications will be sent after a new date has been arranged.
Posted Oct 09, 2025 - 15:48 BST

Scheduled

To support future growth and provide improved network capacity and reliability, we will be upgrading network devices at our Virtus LON1 Enfield Datacentre.

When: Thursday 16th October 2025, 21:00 BST – Friday 17th October 2025, 06:00 BST

Most customers will not experience any outage, though some network services will run with reduced redundancy during the maintenance window. Customers without resilient connections could see short service interruptions.

A small number of customers may be more directly affected — those customers will be contacted individually.

Thank you for your understanding while we carry out these important improvements.
Posted Oct 02, 2025 - 17:18 BST
This scheduled maintenance affected: DC Connect, IP Transit Services, Leased Lines and Datacentres (Virtus LON1 Enfield).