Virtual Data Centre - Enfield Cluster migration

Scheduled for Jul 26, 10:00 BST  -  Jul 27, 22:00 BST

Scheduled

EXN will be performing essential maintenance on our Virtual Data Centre (vDC) platform.
As part of this process we will be migrating the Enfield vDC to a new cluster.

No downtime is expected, but please note that virtual machines (VMs) should be considered at risk during the migration.
Each client vDC will be migrated individually. Some management functions may be temporarily impacted during this time.

This procedure has been tested in our lab environment, and we expect any disruption to be minimal.

Location: Virtus Enfield
Start: 2025-07-26 - 10:00 BST (UTC +1)
End: 2025-07-27 - 22:00 BST (UTC +1)
Affected Services: Virtual Machines and VMware vDC Management Functions
Reason: Cluster migration
Classification: At Risk (for running VMs) - Intermittent disruption management functions
Posted Jul 04, 2025 - 15:05 BST
This scheduled maintenance affects: Virtual Data Centre (vDC) - Virtus Enfield.